266x Filetype XLS File size 0.08 MB Source: www.tamuk.edu
Sheet 1: CSP Project Checklist
| Form | Status/Information | Date | Entered By: | ||||
| Y | 2 | Pre-Construction Phase | |||||
| 3 | Project Name: | ||||||
| 4 | Project Number/User Ref:, see 209 | ||||||
| 5 | Project FAMIS Acct Number: | ||||||
| 6 | Commodity Code: | ||||||
| 7 | Project Total Budget: | ||||||
| 7A | Less: 10 % Contingency Minimum | ||||||
| 7B | Asbestos Abatement & Testing | ||||||
| 7C | Compaction Testing | ||||||
| 7D | Concrete Testing | ||||||
| Y | 7E | Key Cores | |||||
| 7F | Moisture Testing | ||||||
| Y | 7G | Newspaper | |||||
| 7H | Soil Core Testing | ||||||
| 7I | Utility Easements | ||||||
| 7J | Test and Balances | ||||||
| 7K | TDLR Fee | ||||||
| 7L | Windstorm Certification | ||||||
| 8 | Amt Available for A/E & Const Contract | ||||||
| 9 | Project Manager: | ||||||
| 10 | Project Manager Phone: | ||||||
| 11 | Project Manager Email: | ||||||
| 12 | Program of Requirement, see 210 | ||||||
| 13 | A/E Needed?, >$8,000 | ||||||
| 14 | A/E Selection | ||||||
| 15 | A/E Contact Information | ||||||
| 16 | A/E Contract Amount | ||||||
| 17 | A/E Requisition Doc | C-32 | |||||
| 18 | A/E Contract Number | ||||||
| 19 | C-30 Reviewed with A/E | ||||||
| 20 | Contract Type: (CSP, JOC, DB, CMR,) see 211 | ||||||
| Y | 21 | Contract Documents | |||||
| 22 | Bid Package | ||||||
| 23 | Project Specifications (Div. 1-16) | ||||||
| 24 | Uniform General Conditions, see 212 | C-8 | |||||
| 25 | Supplemental General Conditions, see 213 | C-9 | |||||
| 26 | Special Conditions, see 214 | ||||||
| Y | 27 | Considerations | |||||
| 28 | Subcontracting Opportunities? | ||||||
| 29 | HSP Required? >$100,000 | ||||||
| 30 | Bid Bond Required? >$25,000 | C-2 | |||||
| 31 | Payment Bond Required? >$25,000 | C-7 | |||||
| 32 | Performance Bond Required? >$100,000 | C-6 | |||||
| 33 | Form | Status/Information | Date | Entered By: | |||
| Y | 34 | Competitive Bid Check List | |||||
| Y | 35 | Bid Opening Date/Time | |||||
| 36 | Invitation for Bid | C-3 | |||||
| Y | 37 | Pre Bid Conference Date & Room: | |||||
| 38 | Pre Bid Conference Site: | ||||||
| 39 | FAMIS R Doc Number | ||||||
| 40 | R Doc Submitted to Routing (Date) | ||||||
| 41 | Bids Required: | ||||||
| 42 | Bid Number: | ||||||
| 43 | ESBD Posting Required? >$25,000 | ||||||
| 44 | ESBD Posting Date: | ||||||
| 45 | Newspaper R Doc 1 | ||||||
| 46 | Newspaper R Doc 2 | ||||||
| 47 | Ad Dates | ||||||
| 48 | Bid Addendum 1 Posted | ||||||
| 49 | Bid Addendum 2 Posted | ||||||
| 50 | Bid Addendum 3 Posted | ||||||
| 51 | Bids Opened On: | ||||||
| 52 | Bid Opening Presiding Officer (SSGS) | ||||||
| Y | 53 | HSP Reviewed & Approved By: | |||||
| Y | 54 | C-10 Routing and Approvals | |||||
| Y | 55 | C-10 Recommended by PM | C-10 | ||||
| Y | 56 | C-10 Certified by SSGS | C-10 | ||||
| 57 | Contract No. Assigned by SSGS (Date) | C-10 | |||||
| 58 | Contract Number: | C-10 | |||||
| Y | 59 | C-10 Signed by VPFA (Date) | C-10 | ||||
| 60 | Contract Awarded: | ||||||
| 61 | Ground Breaking Ceremony? | ||||||
| 62 | |||||||
| 63 | |||||||
| 64 | Form | Status/Information | Date | Entered By: | |||
| Y | 65 | Contractor Information | |||||
| 66 | Contractor: | ||||||
| 67 | Contractor Rep: | ||||||
| 68 | Contractor Rep Phone: | ||||||
| 69 | Contractor Rep Email: | ||||||
| 70 | |||||||
| 71 | Notification Letter Sent to Contractor, see 215 | ||||||
| 72 | Contract Sent to Contractor, see 216 | ||||||
| 73 | Insurance Received (Date) | ||||||
| 74 | Payment Bond Received (Date) | ||||||
| 75 | Performance Bond Received (Date) | ||||||
| 76 | Contract Signed by Contractor (Date) | ||||||
| 77 | Contract Signed by PM (Date) | ||||||
| 78 | Contract Signed by SSGS (Date) | ||||||
| 79 | Contract Signed by VPFA (Date) | ||||||
| 80 | Contracts Distributed (Date), see 217 | ||||||
| 81 | Spreadsheet Posted on Server, Procurement (Date) | ||||||
| 82 | Pre Construction Meeting Notice Mailed (Date) | ||||||
| 83 | Pre Construction Meeting (Date): | ||||||
| 84 | C-30 Reviewed with Contractor | ||||||
| 85 | Dig Permit? | ||||||
| 86 | Notice to Proceed to Contractor (Date) | ||||||
| 87 | Construction Schedule Received | ||||||
| 88 | Schedule of Values Received | ||||||
| 89 | Notify Property Manager of Utility changes | ||||||
| 90 | Record all meter readings for utility useage, if applicable | ||||||
| 91 | |||||||
| 92 | |||||||
| 93 | Form | Status/Information | Date | Entered By: | |||
| Y | 94 | Construction Phase Documents | |||||
| 95 | Asbestos Abatement - Results | ||||||
| 96 | Compaction Testing - Results | ||||||
| 97 | Concrete Testing - Results | ||||||
| Y | 98 | Key Core Plan | |||||
| 99 | Moisture Testing - Results | ||||||
| 100 | Soil Core Testing - Results | ||||||
| 101 | Utility Easements - Results | ||||||
| 102 | Test and Balances - Results | ||||||
| 103 | TDLR Inspection | ||||||
| 104 | Windstorm Certificate | ||||||
| 105 | Inspection Report | ||||||
| Y | 106 | Reoccuring Documents | |||||
| 107 | Payment No. 1 (Amount/Date) | ||||||
| 108 | Change Order No 1. Amount/Date | C-21/11 | |||||
| 109 | Substantial Completion | ||||||
| Y | 110 | Pre-Project Close-Out | Complete/Received? Yes/No/NA | Date | Entered By: | ||
| 111 | Payment Received for Contractor Utility Use | ||||||
| 112 | Beneficial Occupancy (Date), see 218 | ||||||
| 113 | Equipment startup/proofing | ||||||
| 114 | Operator training | ||||||
| 115 | O&M Manuals | ||||||
| 116 | As built Drawing Received (Date) | ||||||
| 117 | Shop Drawings and Submittals | ||||||
| 118 | Letter of Warranty Received (Date) | ||||||
| 119 | Product Warranties received | ||||||
| 120 | Spare Parts and Materials | ||||||
| 121 | Keys (Contractors/Users) | ||||||
| 122 | Contractor Site Clean-up | ||||||
| 123 | NFPA Inspection, see 219 | ||||||
| 124 | TDLR-ADA Insp. >$50,000.00, see 220 | ||||||
| 125 | TDSHS insp. >$50,000.00, see 221 | ||||||
| 126 | Telecom; (Cable, TTVN) | ||||||
| 127 | Project Manager Inspection | ||||||
| 128 | Final punchlist established | ||||||
| 129 | Final Inspection Date Established | ||||||
| 130 | Report of substantial Completion | C13a | |||||
| 131 | Ribbon Cutting Ceremony? | ||||||
| 132 | |||||||
| Y | 133 | STAFF REVIEW | Accepted? Yes/No/NA | ||||
| 134 | (E-mail notice, 24hr response time) | ||||||
| 135 | Director of CIS | ||||||
| 136 | Director of Physical Plant | ||||||
| 137 | Director of Risk Management | ||||||
| 138 | Director of Engineering & Planning | ||||||
| 139 | Director of University Police | ||||||
| 140 | Executive Director of Facilities | ||||||
| Y | 141 | Final Project Close-Out | Completed? Yes/No/NA | Date | Entered By: | ||
| 142 | All punchlist items completed | ||||||
| 143 | Final Payments to Sub-Contractors | ||||||
| 144 | Release of Liens | ||||||
| 145 | Engineer/Architect letter of acceptance | ||||||
| 146 | Report of Final Acceptance | C-13b | |||||
| 147 | CIP Closeout Report Filed (Date) | ||||||
| 148 | |||||||
| Y | 149 | Contract Close-Out | Completed? Yes/No/NA | ||||
| 150 | Construction costs distributed by FAMIS Code | C-30 | |||||
| 151 | attach | ||||||
| 152 | Verify project total amounts match pay requests | ||||||
| 153 | |||||||
| 154 | Verify all accounts included | ||||||
| 155 | Copy of FAMIS breakouts to Property Management | ||||||
| 156 | |||||||
| 157 | Final Change Order and Adjustments | ||||||
| 158 | Final Payment Authorization | C-19 | |||||
| 159 | Terms: | ||||||
| 160 | |||||||
| 161 | A/E - Architect or Engineer | JOC - Job Order Contract | |||||
| 162 | ADA - Americans with Disabilities Act | O&M - Operation and Maintenance | |||||
| 163 | CIS - Computer Information System | P Doc - Purchase Order | |||||
| 164 | CMR - Construction Manager at Risk | PM - Project Manager | |||||
| 165 | CSP - Competitive Sealed Proposal | POR - Program of Requirements | |||||
| 166 | DB - Design Build | R Doc - Requisition Order | |||||
| 167 | ESBD - Electronic State Business Daily | SSGS - Strategic Sourcing and General Services | |||||
| 168 | FAMIS - Financial Accounting Management Information System | TDH - Texas Department of Health | |||||
| 169 | HSP - HUB Sub Plan | TDLR - Texas Department of Licensing and Regulation | |||||
| 170 | HUB - Historically Underutilized Business | VPFA - Vice President for Finance and Administration | |||||
| 171 | |||||||
| 172 | |||||||
| 173 | Footnotes: | ||||||
| 174 | |||||||
| 175 | Project Number must be inserted as User Ref: on all Requistions | ||||||
| 176 | Scope of Design and Work; Budget; and Schedule | ||||||
| 177 | Job Order Contract and Design Build have additional items for review on the next tab | ||||||
| 178 | Uniform document for state projects >$25,000 | ||||||
| 179 | Document stating any changes in policy to the Uniform General Conditions | ||||||
| 180 | Documents specific to a project | ||||||
| 181 | Notification Letter must requests insurance, bonds, and pre-construction date. Signed C-10 and 3-copies of contract attached | ||||||
| 182 | 3- Copies Attached with Notification Letter | ||||||
| 183 | Copies to Contractor, Procurement, and Project Manager | ||||||
| 184 | Before final completion, owner may occupy | ||||||
| 185 | National Fire Prevention Association Inspection | ||||||
| 186 | Texas Department of Licensing and Regulation (Boilers, Elevators, etc…) | ||||||
| 187 | Texas Department of State Health Services | ||||||
| 188 | Add additional rows if there are multiple Inspections Reports or list a directory where they can be found. | ||||||
| 189 | Add additional rows if there are multiple Payment Applications or list a directory where they can be found. | ||||||
| 190 | Add additional rows if there are multiple Change Orders or list a directory where they can be found. | ||||||
| 191 | TDLR inspection to be done before Final Project Closeout. | ||||||
| Y | CIS Considerations | Completed? Yes/No/NA | Date | Entered By: | |||
| Locate underground cable (fiber, telephone, etc.,) | |||||||
| Cable route from building to network infrastructure | |||||||
| Cable requirements (CAT6, fiber, telephone) | |||||||
| Card reader requirements | |||||||
| Video surveilance requirements | |||||||
| Multimedia rooms (audio, visual) | |||||||
| Computer labs | |||||||
| TTVN Room | |||||||
| Network equipment (wired, wireless) | |||||||
| Emergency notification system | |||||||
| Kiosk | |||||||
| Telecom requirements (MDF, IDF) | |||||||
no reviews yet
Please Login to review.