Sheet 1: Construction Gantt Chart
| KWA | |||||||||||||||
| Project: | JJM -Kannur Dt.Madayi Pt | ||||||||||||||
| Construction site: | Madayi Panchayath | ||||||||||||||
| Construction Activities | DURATION (Days) |
||||||||||||||
| START DATE | END DATE | DESCRIPTION | |||||||||||||
| 6/10/21 | 7/31/21 | Supply of pipe | 51 | ||||||||||||
| 6/10/21 | 6/22/21 | earth work of sump at kambipalam | 12 | ||||||||||||
| 7/1/21 | 7/10/21 | earth work of sump at memala | 9 | ||||||||||||
| 6/23/21 | 9/24/21 | concrete work of sump at kambipalam | 91 | ||||||||||||
| 9/25/21 | 12/25/21 | concrete work of sump at memala | 90 | ||||||||||||
| 9/1/21 | 12/31/21 | pipe laying work | 120 | ||||||||||||
| 1/1/22 | 2/25/22 | finishing work and tank connections of sump | 54 | ||||||||||||
| 2/26/22 | 3/15/22 | trial running and commissioning | 19 | ||||||||||||
| USEFUL TIPS | |
| 1 | When enteringactivity start and end dates in columns "C" and "D" use the following date format: DD/MM/YYYY |
| 2 | To change colour of fill and text in cells, use HOME -> FONT tool palette. |
| 3 | To change the start date shown on the gantt chart: Fotmat -> (Current Selection tab) Format Selection -> Axis Options -> Bound: Minimum -> Change value to a number that will be appropriate for your project start date. e.g. 43831 = 1/1/2020 44197 = 1/1/2021 44562 = 1/1/2022 ..... |
no reviews yet
Please Login to review.