Periods Period Days Complexity_Factor CF_Days
Nominations - SAR / PR 60Action Deferred 30
SP1 - SAR/PR/WP Posting 1 60Additional Comment/Ballot 60
SP2 - SAR/PR/WP Posting 2 60Additional Outreach 30
Nominations - DT 60Change in Approach 90
CP1 - Comment Period 1 45Change in Developer 30
CP2 - Comment Period 2 45Cross-Coordination (Finish-Start) 90
QR - Quality Review 30Cross-Coordination (Parallel) 90
CIB - Com/Ballot 1 (Initial) 80Directive Added to Scope 60
CAB - Com/Add Ballot 2 80Eliminated Comment Period -60
CAB - Com/Add Ballot 3 Field Test 365
CAB - Com/Add Ballot 4 Highly Technical 90
CAB - Com/Add Ballot 5 Industry Survey 30
FB - Final Ballot 30Intentional Hold/Delay 30
PTB - Present to BOT N/A 0
Filing - Filing with Regulators Pandemic 90
PT - Post Approval Training Posting Conflict 7
550Project Split or Phased -60
Research Required 180
RSDP Priority Decrease 60
RSDP Priority Increase -60
SAR - Revised/Additional Posting 60
SAR - Supplemental 60
SC Appoints SAR Team as SDT -60
Schedule Too Aggressive 90
Schedule Too Conservative -90
Standard Added to Scope 60
Standard Developer Change 30
Supplemental members 60
Periods Period Days Complexity_Factor CF_Days
Team Augmented 60
Team Coordination (e.g., Weather) 30
Team Coordination/Availability 30
Technical Work Required 180
Unplanned Team Meeting 30
Unplanned Technical Workshop 30
project_tracking_spreadsheet.xlsx Home
Updated:7/18/2022
Baseline / Complexity 2015 2016 2017
Status HOME DO NOT SORT (Filtering Ok) Early/(Late) Factor / Status Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Index Update List of Approved Projects (Filter) Deliverables (Filter) Days (Filter) (Filter) Filter ###########################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################################
44Yellow 2016-02d - Modifications to CIP Standards Address all remaining V5TAG -437Working to Initial Ballot
58Yellow 2017-01b - Modifications to BAL-003-1.1 BAL-003-3 -224SAR / PR / WP
88Yellow 2019-04 - Modifications to PRC-005-6 PRC-005 28SAR / PR / WP
96Yellow 2020-02 - Transmission-connected Resources PRC-024 -292SDT Development
98Yellow 2020-03 - Supply Chain Low Impact Revisions CIP-003-8 -116SDT Development
100Yellow 2020-04 - Modifications to CIP-012-1 CIP-012-2 -143SDT Development
104Yellow 2020-06 - Verifications of Models and Data for Generators MOD-026, MOD-027 181SDT Development
106Yellow 2021-01 - Modifications to MOD-025 and PRC-019 PRC-019, MOD-025 84SDT Development
108Yellow 2021-02 - Modifications to VAR-002-4.1 TBD 150SDT Development
110Yellow 2021-03 - CIP-002 Transmission Owner Control Centers (TOCC) TBD -6SDT Development
112Yellow 2021-04 - Modifications to PRC-002-2 TBD -61Working to Initial Ballot
114Yellow 2021-05 - Modifications to PRC-023-4 PRC-023-5 -173SDT Development
116Yellow 2021-06 - Modifications to IRO-010 and TOP-003 TBD 90SDT Development
118Yellow 2021-07 - Extreme Cold Weather Grid Operations, Preparedness, and Coordination TBD 458SDT Development
120Yellow 2021-08 - Modifications to FAC-008-5 TBD -203SDT Development
122Yellow 2022-01 - Reporting ACE Definition and Associated Terms TBD 0SDT Development
124Yellow 2022-02 - Modifications to TPL-001-5.1 and MOD-032-1 TBD -170SDT Development
126Yellow 2022-03 - Energy Assurance with Energy-Constrained Resources TBD 0Nominations & SAR
NERC (Public) Printed on: 08/14/2022 3 of 133
project_tracking_spreadsheet.xlsx Summary
Priority in No. of Directionally
Project Project Name Status Comments Deliverable Deadline RSDP, click to P81 Req Number of Guidances consistent with IERP Developer PMOS Affected Last
see applicable (2013) Directives (see Note 2) findings (See Note 5) Liaison Standards Updated
Footnote
SUMMARY (Sorting okay) (Sorting okay) (Sorting okay) (Sorting okay) (Sorting (Sorting okay) (Sorting (Sorting (Sorting (Sorting okay) (Sorting (Sorting (Sorting HOME
okay) okay) okay) okay) okay) okay) okay)
Address all remaining
V5TAG issues: Cyber
Asset and BES CA (BCA)
definitions, Network and
Externally Accessible
The SDT worked on responses to themes derived from Industry Devices (ESP, ERC, IRA), Ken
Working to Initial responses from the September ballot and comment. A 45-day Obligations, Footnote 11, Lanehome CIP-004, CIP-005,
2016-02d Modifications to CIP Standards Ballot formal comment period for the CIP Virtualization suite of standards Virtualization, and CIP N/A Medium N/A 1 0 N/A Jordan Mallory (primary), Kirk CIP-006, CIP-007 7/18/2022
(outlined below) is open through 8 p.m. Eastern Monday, April 4, Exceptional Rosener and CIP-010
2022 (Draft 3). Now extended to April 11, 2022. Circumstances. Team is (secondary)
working on CIP-007 and
CIP-010 while CIP-005
and the associated
definitions are out for
comment.
The SDT met on January 25, February 16, and 24, 2022. The SDT will Linda Lynch
complete instructions for the Form industry will use to complete Footnote 11, (primary),
2017-01b Modifications to BAL-003-1.1 SAR / PR / WP data submittals. The SDT will also complete the revisions to BAL-003-3 N/A Medium N/A 0 0N/A Laura Anderson Pamela BAL-003-2 7/18/2022
Attachment A. Hunter
(Backup)
In the SC's February 16, 2022 meeting, SC appointed the additional
candidates for Project 2019-04 Modifications to PRC-005-6 to the
Project 2019-04 Standard Drafting Team (SDT), as recommended by Joseph Gatten
NERC staff. The team divided into three sub-teams to work on the (primary),
2019-04 Modifications to PRC-005-6 SAR / PR / WP following issues: Definition approach; Minimum Facilities; and PRC-005 12/30/1899Footnote 11, Low N/A 0 0N/A Laura Anderson Linda Lynch PRC-005-6 7/18/2022
Battery. The SDT met for the 1st time on February 18, 2022 to begin (secondary)
work on revisions to the Standard’s requirements. The sub-teams
are conducting meetings and will bring their work to the SDT for
vetting.
NERC (Public) Printed on: 08/14/2022 4 of 133