INDEPENDENT COST ESTIMATES
AND COST REVIEWS
2
E = Mc = TPC But what
= should it
really cost?
Michael Peek, PE CCE CFM
Why Independent Cost Estimates
and Cost Reviews?
We cannot solve our problems with the same thinking we used
when we created them.
Albert Einstein
• Support Secretarial/Acquisition Executive decision
making
• Logical “next step”… increase focus on front-end
planning
• Address External Stakeholder Concerns
– Consistent with GAO Best Practices Guidelines (GAO-09-3SP)
– Adopt Industry Standards
• Requirements addressed in DOE O 413.3B
• Statutory requirement … mandated in FY2012
Consolidated Appropriations Act (P.L. 112-74)
DOE O 413.3B Requirements
If you can't explain it simply, you don't understand it well enough.
Albert Einstein
• With the implementation of DOE Order 413.3B, Program and
Project Management for the Acquisition of Capital Assets, the
Office of Engineering and Construction Management is
required to conduct an Independent Cost Review (ICR) and/or
develop an Independent Cost Estimate (ICE) to support the
Secretarial Acquisition Executive’s (SAE)/Acquisition
Executive’s (AE) decision at various Critical Decision (CD)
milestones …
Requirement DOE O 413.3B
• For projects > $750M, OECM must conduct ICR prior to CD-0
• For projects > $100M, OECM must conduct:
Prior to CD-1, ICE and/or ICR
Cost Reviews Prior to CD-2, ICE
(App C, Sec 18.) Prior to CD-3, ICE (if warranted)
FY2012 Consolidated Appropriations
Act Requirements (P.L. 112-74)
A perfection of means, and confusion of aims, seems to be our
main problem.
Albert Einstein
• Sec 308: None of the funds made available in this
title may be used to approve critical decision-2 or
critical decision-3 under Department of Energy
Order 413.3B, or any successive departmental
guidance, for construction projects where the total
project cost exceeds $100,000,000, until a separate
independent cost estimate has been developed for
the project for that critical decision.
Best Practices
The only source of knowledge is experience.
Albert Einstein
• GAO Cost Estimating and Assessment Guide: Best
Practices for Developing and Managing Capital
Program Costs, March 2009 (GAO-09-3SP)
• Association for the Advancement of Cost Engineering
International (AACEI)
– Recommended Practices
– Professional Practice Guides
• Society of Cost Estimating and Analysis (SCEA)
– Cost Estimating Body of Knowledge (CEBok)
• DOE G 413.3-21 Cost Estimating Guide, May 2011