335x Filetype PDF File size 0.27 MB Source: atimysore.gov.in
Chapter 6
Project Implementation and Tools
Tools for Project Scheduling
The project manager uses a planning and scheduling process because most projects are
complex, of long duration, require visualization of their parts and the resources needed.
A planning and scheduling process:
• Identifies project activities (tasks/steps)
• Identifies the sequence and duration of project activities
• Organizes project resources (labor, equipment, materials, technology, facilities)
• Enables monitoring of project progress
In any project:
There will be many tasks to accomplish.
Tasks have to go through a sequence
Some tasks cannot start until others are finished (task dependency)
Some tasks are unconstrained.
Some are “critical tasks”
Some task will have flexibility in time, cost, resources
Some tasks will have uncertainty
Project scheduling involves determination of precedence relationship between work
elements(activities) determining extent of interdependency and developing the flow path of the
activities to reach the objectivities of the project.
Steps in Project Scheduling
1. Develop Work Breakdown Structure(WBS) to establish work elements constituting the
project
2. Determine Interdependency among various work elements or activities/tasks and
accordingly define logical sequence of the activities
3. Quantify each work element in terms of time/other resources requirements
4. Find out constraints, if any, external(e.g., Government policies, law and order problem,
inadequacies of infrastructure etc.). and internal(e.g., poor choice of site, inadequacies in
agreement with other stakeholders such as consultants etc.)
5. Review the work elements, their inter dependencies and quantification in light of the
identified constraints
6. Develop a flow path of activities satisfying the logic of interdependency and constraints
7. Develop a time schedule of activities satisfying the logic of the flow path and time
duration of the activities.
165
Work Breakdown Structure (WBS)
First step toward a work plan
Helps to identify the tasks in a project
The concept of the WBS is simple: in order to manage a whole project, one must
manage and control each of its parts
What is a Work Breakdown Structure?
◙ The WBS is a graphical display of the project.
◙ WBS is a hierarchical listing of the sub-components of a project
◙ What is the purpose of the WBS?
The purpose of the WBS is to divide the total project into small pieces, sometimes called
work packages.
Dividing the project into work packages makes it possible to prepare project schedules
and cost estimates and to assign management and task responsibility
WBS components
Tasks
Dependencies
Start date
Duration
Resources
Milestones
Deliverables
The WBS should be divided into tangible deliverable items (hardware items, software
packages, interim reports in R & D, etc.).
WBS levels?
Typically 6 or fewer
1 Total project
2 Sub-project
3 Combination of tasks
4 Task
5 Sub-task
6 Individual processes or actions
At what level do you stop?
• Stop when you reach a point at which you can estimate required resources to the desired
degree of accuracy
• Or when the work will take an amount of time equal to the smallest units you want to
schedule days, weeks, months, etc.
• Or stop when the element is .5 to 2.0% of the project.
• Or stop once you’ve identified a “work package”
166
A WBS planning key!!
REMEMBER the rule that the people who must do the work should participate in
planning it.
• Different levels may be done by different groups
– Top management may do the first level or two and pass it on down to the
operating levels for further amplification
– Software can help
A Gantt chart is a horizontal bar chart developed as a production control tool in 1917 by Henry
L. Gantt, an American engineer and social scientist. Frequently used in project management, a
Gantt chart provides a graphical illustration of a schedule that helps to plan, coordinate, and
track specific tasks in a project. It is a simple and widely used method of working out and
displaying the knotty problem of who does what and when. Typically it is used in a project
where a number of people are working on interlinked tasks.
How does it work?
The basic principle of the Gantt Chart is to show time in a number of columns and to draw bars
across those columns in order to show the usage of time. Each bar represents a task being
carried out by one or more people. The bars can be summed downwards into simple histograms
to show whether individuals are double-booked or have spare time on their hands.
167
Additional symbols and colours may be added to the chart to show events and features such as
milestones (zero-length tasks), critical paths (which, if extended, will slip the completion date
of the project) and float (where tasks can be slipped without jeopardizing the completion date).
Characteristics of Gantt/Bar Chart
Popular tool for project scheduling
Graph with bar representing time for each task
Provides visual display of project schedule
Doesn’t show priorities
Gantt charts may be simple versions created on graph paper or more complex automated
versions created using project management applications such as Microsoft Project or
Excel.
How do you do it?
1. Break down the task into units that can be clearly allocated and tracked. In a typical project
this might be tasks of one week or less, allocated to one person each (although this can vary
widely with the type of project).
2. Identify skills and resources required by each task and allocate the task to a person or group,
along with appropriate resources. Be careful when allocating scarce resources, such as subject
specialists or expensive equipment; a person with less skill who can perform the task, albeit
over a longer period, can free up the expert for working on more critical activities.
168
no reviews yet
Please Login to review.